Dominion proposes 800 MW of new solar and storage in Virginia

The proposal includes 10 solar and energy storage projects, totaling nearly 500 MW, that will be owned and operated by Dominion Energy Virginia.
Follow @EngelsAngle

Dominion Energy Virginia has asked state regulators to approve nearly two dozen new solar and energy storage projects totaling 800 MW of capacity.

The proposal includes 10 solar and energy storage projects, totaling nearly 500 MW, that would be owned and operated by Dominion Energy Virginia. The proposal also includes power purchase agreements (PPAs) with 13 solar and energy storage projects, totaling more than 300 MW, that are owned by independent developers. The PPAs were selected through a competitive solicitation process.

The projects are part of Dominion Energy Virginia's third annual clean energy filing and must be approved by the Virginia State Corporation Commission. The proposed utility-owned projects require local and state permits before construction may begin.


Subscribe today to the all-new Factor This! podcast from Renewable Energy World. This podcast is designed specifically for the solar industry and is available wherever you get your podcasts.

Listen to the latest episode featuring cleantech communications veteran Mike Casey and SOLV Energy CEO George Hershman. They discuss building true political power in clean energy and how to overcome NIMBY efforts in communities.


If approved, the projects are expected to be completed between 2023 and 2025, and would add around $0.38 to the average residential customer's monthly bill. 

Construction could support nearly 4,800 clean energy jobs and generate more than $920 million in economic benefits across Virginia, the utility said.

Additional details about the utility-owned projects are below:

Utility-Scale Solar
Bridleton Solar20 MWHenrico CountyAcquired from Vega Renewables, LLC
Cerulean Solar62 MWRichmond CountyTo be acquired from Strata Clean Energy
Courthouse Solar167 MWCharlotte CountyAcquired from NOVI Energy
King's Creek Solar20 MWYork CountyAcquired from KDC Solar Virginia
Moon Corner Solar60 MWRichmond CountyDeveloped by Dominion Energy Virginia
North Ridge Solar20 MWPowhatan CountyAcquired from North Ridge Powhatan Solar, LLC
Southern Virginia Solar125 MWPittsylvania CountyAcquired from Strata Clean Energy
Distributed Solar
Ivy Landfill Solar3 MWAlbemarle CountyTo be acquired from Community Power Group
Racefield Solar3 MWJames City CountyAcquired from Hexagon
Utility-Scale Energy Storage
Shands Storage15.7 MWSussex CountyAcquired from East Point Energy

The projects are expected to help meet requirements of the Virginia Clean Economy Act's (VCEA) renewable portfolio standard, which requires Dominion Energy Virginia to generate 100% of its electricity from carbon-free sources by 2045.

Two of the projects – Kings Creek Solar and Ivy Solar – would be built on previously developed land in support of the VCEA's requirement for at least 200 MW of solar on brownfield sites.

Data & News supplied by www.cloudquote.io
Stock quotes supplied by Barchart
Quotes delayed at least 20 minutes.
By accessing this page, you agree to the following
Privacy Policy and Terms and Conditions.
 
 
Copyright © 2010-2020 MenloPark.com & California Media Partners, LLC. All rights reserved.