BHP BILLITON ANNOUNCES INCREASE IN IRON ORE AND MANGANESE RESOURCES AND RESERVES

BHP Billiton announced a 46 per cent increase in the Mineral Resource and a 23 per cent increase in the Ore Reserve at Western Australia Iron Ore, an 11 per cent increase in the Mineral Resource and a 30 per cent increase in the Ore Reserve at Samarco Mineracao and an 82 per cent increase in the Mineral Resource at Samancor Manganese. Work is in progress to incorporate the new Manganese Resource and estimate its impact on Manganese Reserves.

Western Australia Iron Ore Mineral Resource and Ore Reserve upgrade

The Western Australia Iron Ore Mineral Resource increased by 3.7 billion wet metric tonnes (tonnes) to 11.7 billion tonnes, and the Ore Reserve increased by 571 million wet tonnes to 3 billion tonnes, both in 100 per cent terms. BHP Billiton’s attributable share of the Mineral Resource is 10.3 billion tonnes and Ore Reserve is 2.6 billion tonnes.

In 100 per cent terms, approximately 2.3 billion tonnes of Mineral Resource has been defined at the Jinayri and Marillana deposits, 1 billion tonnes has been defined at Area C and Yandi, and 442 million tonnes has been defined at the Eastern Pilbara mining hub.

The strategy to blend Yarrie (Mt Goldsworthy JV - Northern) mine production with Newman and Mining Area C mine production has resulted in an increase in the Yarrie Mineral Resource to 171 million tonnes and in an increase in the Yarrie Ore Reserve to 24 million tonnes in 100 per cent terms.

In 100 per cent terms, the increase in Ore Reserves includes 180 million tonnes of Brockman ore at Packsaddle (Mining Area C), 41 million tonnes of Brockman ore at Newman, 172 million tonnes of Brockman ore at Jimblebar and 178 million tonnes of Channel Iron Deposit ore at Yandi.

Full details are provided in Figures 1, 2 and 3, and Tables 1 and 2.


Samarco Mineral Resource and Ore Reserve upgrade

In 100 per cent terms, the Samarco Mineral Resource increased by 327 million dry tonnes to 3.3 billion tonnes and the Ore Reserve increased by 144 million dry tonnes to 624 million tonnes. BHP Billiton’s attributable share of the Mineral Resource and Ore Reserve is now approximately 1.7 billion tonnes and 312 million tonnes respectively. Full details are provided in Tables 1 and 2.

Samancor Manganese Mineral Resource changes

Samancor Manganese Mineral Resource has increased by 213 million dry tonnes to 473 million tonnes, in 100 per cent terms. The increase is mainly due to the inclusion of the Upper Body at Wessels Mine and the Top Cut at Mamatwan mine, along with the signing of the agreement1 between Samancor Manganese and Ntsimbintle Mining Pty Ltd, a Black Economic Empowerment (BEE) party in the Kalahari. Consent has been given by the Minister to the Ntsimbintle transaction on a section 11 application (the vending of the prospecting rights into an existing mining right); Samancor Manganese Pty Ltd is still awaiting the letter of consent and approval. BHP Billiton’s interest in the total Mineral Resource in South Africa has reduced from 60 per cent to 54.6 per cent as a result of the transaction. BHP Billiton’s total attributable share of the Manganese Mineral Resources is now 267 million tonnes. Full details are provided in Table 3.

Competent Person’s Statement

The statement of Mineral Resources and Ore Reserves being presented has been produced in accordance with the Australasian Code for Reporting of Mineral Resources and Ore Reserves, December 2004 (the JORC Code). This information is based on information prepared by the relevant Competent Persons and relates to Mineral Resources and Ore Reserves forecast as at 30 June 2008. Competent Persons are named in footnotes to Tables 1, 2 and 3.

All Competent Persons are full time employees of BHP Billiton (unless otherwise stated), have sufficient experience relevant to the style of mineralisation and type of deposit under consideration and to the activity they are undertaking to qualify as a Competent Person as defined in the JORC Code. All Competent Persons are members of either the Australian Institute of Mining & Metallurgy (AusIMM) or the Australian Institute of Geoscientists (AIG) or a Recognised Overseas Professional Organisation (ROPO). The Competent Persons consent to the inclusion in this report of the matters based on their information in the form and context in which it appears.

 

 

1

Refer note 4 to table 3.

 

- 2 -


Figure 1. BHP Billiton Iron Ore Tenement holding showing locations of Jinayri and Marillana

LOGO

 

- 3 -


Figure 2. Jinayri map showing deposit outlines, drill hole locations and areas of interpolation versus extrapolation

LOGO

Figure 3. Marillana map showing deposit outline and drill hole locations

LOGO

 

- 4 -


Table 1. Iron Ore Mineral Resource Statement

Iron Ore Customer Sector Group

Mineral Resources

The table below details the total inclusive Mineral Resource for the Iron Ore Customer Sector Group estimated at 30 June 2008 in 100 per cent terms (unless otherwise stated).

 

As at 30 June 2008

  30 June
2007
   
        Measured Resource   Indicated Resource   Inferred Resource   Total Resource   Total
Resource
   

Commodity
Deposit
(1)(2)(3)(4)(5)(6)

  Ore
Type
  Millions
of wet
metric
tonnes
  Grade   Millions
of wet
metric
tonnes
  Grade   Millions
of wet
metric
tonnes
  Grade   Millions
of wet
metric
tonnes
  Grade   Millions
of wet
metric
tonnes
  BHP
Billiton
Interest
%
      %
Fe
  %
P
  %
SiO2
  %
AI2O3
  %
LOI
    %
Fe
  %
P
  %
SiO2
  %
AI2O3
  %
LOI
    %
Fe
  %
P
  %
SiO2
  %
AI2O3
  %
LOI
    %
Fe
  %
P
  %
SiO2
  %
AI2O3
  %
LOI
   

Iron Ore

                                                     

Mt Newman JV (7)

  BKM   416   63.3   0.08   4.4   2.0   2.3   842   61.2   0.09   6.0   2.4   3.3   1,780   60.3   0.13   4.6   2.7   5.8   3,038   61.0   0.11   5.0   2.5   4.6   1,601   85
  MM   30   61.4   0.06   3.1   1.6   6.9   159   59.7   0.06   4.1   2.6   7.1   860   59.5   0.07   4.0   2.5   7.2   1,049   59.6   0.07   4.0   2.5   7.2   905  

Jimblebar (8)(9)

  BKM   144   61.6   0.09   5.3   2.8   3.8   598   60.6   0.11   4.9   3.0   4.9   860   60.1   0.13   4.9   3.0   5.4   1,602   60.4   0.12   4.9   3.0   5.1   1,341   100
  MM   —     —     —     —     —     —     —     —     —     —     —     —     20   60.2   0.11   3.3   2.7   6.9   20   60.2   0.11   3.3   2.7   6.9   20  

Mt Goldsworthy JV Northern (10)

  NIM   26   61.1   0.06   8.3   1.4   2.4   105   61.8   0.05   7.6   1.1   1.8   40   61.3   0.05   9.0   1.2   1.5   171   61.6   0.05   8.0   1.2   1.8   157   85

Mt Goldsworthy JV Area C (11)(12)

  BKM   102   60.0   0.14   4.1   2.8   6.2   331   59.0   0.13   5.5   2.9   6.3   850   58.7   0.13   6.3   2.6   6.2   1,283   58.9   0.13   5.9   2.7   6.2   1,070   85
  MM   206   62.1   0.06   3.1   1.7   6.0   301   60.7   0.06   4.2   2.1   6.3   430   61.8   0.06   3.3   1.8   6.1   937   61.5   0.06   3.5   1.9   6.1   798  

Yandi JV (13)(14)

  BKM   —     —     —     —     —     —     —     —     —     —     —     —     1,080   59.3   0.14   4.8   2.3   7.2   1,080   59.3   0.14   4.8   2.3   7.2   190   85
  CID   1,125   56.7   0.04   6.0   1.7   10.7   519   56.1   0.04   6.8   1.9   10.7   200   56.7   0.04   6.2   2.1   10.4   1,844   56.6   0.04   6.3   1.8   10.7   1,246  

BHP Billiton Minerals

  BKM   —     —     —     —     —     —     —     —     —     —     —     —     240   60.7   0.13   4.3   2.3   6.0   240   60.7   0.13   4.3   2.3   6.0   240   100

BHP Coal

  BKM   —     —     —     —     —     —     —     —     —     —     —     —     280   60.2   0.13   4.1   2.9   6.4   280   60.2   0.13   4.1   2.9   6.4   280   100
  MM   —     —     —     —     —     —     51   60.4   0.06   4.6   2.3   6.1   130   61.9   0.06   3.9   2.1   5.2   181   61.5   0.06   4.1   2.2   5.5   181  
        Millions
of dry
metric
tonnes
  %Fe   %Pc               Millions
of dry
metric
tonnes
  %Fe   %Pc               Millions
of dry
metric
tonnes
  %Fe   %Pc               Millions
of dry
metric
tonnes
  %Fe   %Pc               Millions
of dry
metric
tonnes
   

Samarco JV (15)

  ROM   945   43.6   0.05         1,434   39.7   0.05         927   37.7   0.05         3,306   40.3   0.05         2,979   50

 

(1)      Resources are divided into joint ventures and material types that reflect the various products produced. The bedded ore types are classified as per the host Archaean or Proterozoic banded iron formations. These are BKM – Brockman, MM – Marra Mamba and NIM – Nimingarra. The CID – Channel Iron Deposits are Cainozoic fluvial sediments. ROM – Run of mine for Samarco, comprising itabirites and friable hematite ores.

 

(2)       The resource grades listed, Fe – iron, P – phosphorous, SiO2 – silica, Al2O3 – alumina refer to in situ mass percentage on a dry weight basis. LOI – loss on ignition, refers to loss of mass (dry basis) during the assaying process. Tonnages are based on wet tonnes for Western Australian Iron Ore (WAIO) deposits using the following moisture contents: BKM – 3%, MM – 4%, CID – 8%, NIM – 3.5%. %Pc – phosphorous in concentrate.

 

(3)      Competent Persons – Mt Newman JV: M Wozga (MAusIMM), M Smith (MAusIMM). C Williams (MAIG). Jimblebar: M Smith (MAusIMM), H Arvidson (MAusIMM), M Wozga (MAusIMM). Mt Goldsworthy JV Northern: S Harrison (MAIG), M Wozga (MAusIMM). Mt Goldsworthy JV Area C: D Reid (MAusIMM), C Williams (MAIG). Yandi JV: S Harrison (MAIG), H Arvidson (MAusIMM). BHP Billiton Minerals: S Harrison (MAIG). BHP Coal: H Arvidson (MAusIMM), M Smith (MAusIMM). Samarco JV: L Bonfioli (MAusIMM), employed by Samarco Minerção SA.

 

(4)      Some cut-off grades have been adjusted to align with revised product strategy. Cut-off grades used to estimate resources: Mt Newman JV 50%Fe for Whaleback deposit (which supplies beneficiation feed), 54%Fe for other BKM and MM deposits; Jimblebar 54%Fe for BKM and MM; Mt Goldsworthy JV 55-56.5%Fe for NIM (except Cattle Gorge, Cundaline, Nimingarra A and B – 50%Fe), 54%Fe for BKM and MM; Yandi 52%Fe for CID, 54% for BKM; BHP Coal 54%Fe for BKM, 50-54%Fe for MM; BHP Minerals 54%Fe for BKM.

 

(5)      The Mineral Resources are reported after adjustment for depletion which occurs when the material is mined. For WAIO the adjustments are based on aerial surveys as of the end of March 2008 plus production forecasts for the period April–June 2008. For Samarco, depletion is based on actual production from July 2007 to April 2008 with production forecast for May and June 2008.

 

(6)      The level of detail available from drilling, outcrop and geophysical data, and combined with existing geological mapping and/or operational information was sufficient to support appropriate resource modelling. The resource estimation process followed by BHPBIO is well established and is consistent with standard industry practice. The classification of the resources is based on both qualitative and quantitative approaches, by applying data density, data quality, geological confidence criteria, estimation performance and reconciliation information.

 

(7)       Changes for Mt Newman JV are due to additional resource definition drilling, new geological interpretation and resource models for Jinayri, Whaleback, OB24, OB25 Pit 4 and OB30, and change to cut-off grade for OB29 and OB30 from 58%Fe to 54%Fe. Jinayri (BKM) is an Inferred Resource of 1.4 billion wet metric tonnes being reported for the first time. Inferred Resource for Jinayri has been estimated using interpolation and extrapolation. For Jinayri, interpolated material has a maximum drill spacing of 300m between section lines and 100m between drill holes on the same section. Extrapolated material is based on a sectional projection of 150m (strike) and 50m (section) beyond the drill holes. The proportion of the Inferred Resource that is based on extrapolated data is 15%.

 

(8)      Changes to Jimblebar are due to additional resource definition drilling, new geological interpretation and resource modelling for Jimblebar W1/2. The Mineral Resource at Wheelarra Hill 1 and 2 deposits has increased by 266 million wet metric tonnes, with 150 million wet metric tonnes, upgraded from Inferred Resource to Indicated Resource.

 

(9)      The Jimblebar Resources listed include the Wheelarra Hill 3, 4, 5, 6 and Hashimoto 1 and 2 deposits at Jimblebar in which the Wheelarra Joint Venture participants (BHP Iron Ore (Jimblebar) Pty Ltd (51%), ITOCHU Minerals and Energy of Australia Pty Ltd (4.8%), Mitsui Iron Ore Corporation Pty Ltd (4.2%) and subsidiaries of Chinese steelmakers Magang, Shagang, Tanggang and Wugang (10% each)) have a legal interest. At the commencement of the Wheelarra Joint Venture on 1 October 2005, the Wheelarra Joint Venture participants had a legal interest in 175 million dry metric tonnes of Jimblebar Reserves (Wheelarra Joint Venture tonnes). The effect of the sales contracts entered into between the Wheelarra Joint Venture participants and the Mt Newman Joint Venture participants and other associated agreements is that BHP Billiton (as a Mt Newman Joint Venture participant) has an entitlement to 85% of these Wheelarra Joint Venture tonnes. This disclosure and the financial statements are prepared on this basis.

 

(10)    Changes to Mt Goldsworthy JV Northern are due to a change in cut-off grade from 56.5%Fe to 50%Fe for Cattle Gorge, Cundaline, Nimingarra A and B deposits. A new resource model for Cundaline has been completed based on new resource definition drill holes and geological interpretation.

 

(11)    Changes to Mt Goldsworthy JV Area C are due to additional resource definition drilling, new geological interpretation and resource models for A and B Deposits, and Packsaddle 1 and 3. The total Mineral Resource at A Deposit has increased by approximately 160 million wet metric tonnes. The total Mineral Resource at Packsaddle 1 and 3 deposits has increased by 103 million wet metric tonnes and 111 million wet metric tonnes respectively. For Packsaddle 1 deposit 56 million wet metric tonnes was converted to Measured Resource and 196 million wet metric tonnes to Indicated Resource from Inferred Resource compared to 2007 reported Mineral Resource. Packsaddle 3 deposit, 46 million wet metric tonnes was upgraded to Measured Resource and 136 million wet metric tonnes to Indicated Resource from Inferred Resource.

 

(12)    The Area C Resources listed include C Deposit within Area C in which the POSMAC Joint Venture participants (BHP Billiton Minerals Pty Ltd (65%), ITOCHU Minerals and Energy of Australia Pty Ltd (8%), Mitsui Iron Ore Corporation Pty Ltd (7%) and a subsidiary of POSCO (a Korean steelmaker) (20%)) have a legal interest. The effect of the sales contracts entered into between the POSMAC Joint Venture participants and the Mt Goldsworthy Joint Venture participants and other associated agreements is that BHP Billiton (as a Mt Goldsworthy Joint Venture participant) has an entitlement to 85% of the resources in C Deposit. This disclosure and the financial statements are prepared on this basis.

 

(13)    Changes to Yandi JV are due to a change in CID cut-off grade from 56%Fe to 52%Fe. Other changes are due to additional resource definition drilling, new geological interpretation and resource modelling for Yandi W1 and Marillana (BKM). Marillana, an Inferred Resource, has increased from 190 million wet metric tonnes to 1,080 million wet metric tonnes.

 

(14)    The Yandi Resources listed include the Western 4 deposit in which the JFE Western 4 Joint Venture (JW4 JV) participants BHP Billiton Minerals Pty Ltd (68%). ITOCHU Minerals and Energy of Australia Pty Ltd (6.4%), Mitsui Iron Ore Corporation Pty Ltd (5.6%) and a subsidiary of JFE Steel Corporation (a Japanese steelmaker) (20%)) have a legal interest. The effect of the sales contracts entered into between the JW4 JV participants and the Yandi JointVenture participants and other associated agreements is that BHP Billiton (as a Yandi Joint Venture participant) has an entitlement to 85% of the resources in the Western 4 deposit. This disclosure and the financial statements are prepared on this basis.

 

(15)    The changes to Samarco’s Mineral Resources are due to additional drilling, changes in resource classification criteria, new geological models and changes to the cut-off grades.

 

- 5 -


Table 2. Iron Ore - Ore Reserve Statement

Iron Ore Customer Sector Group

Ore Reserves

The table below details the total Ore Reserves for the Iron Ore Customer Sector Group estimated as at 30 June 2008 in 100 per cent terms (unless otherwise stated).

 

As at 30 June 2008

   As at 30 June 2008     
          Proved Ore Reserve    Proved Ore Reserve    Total Ore Reserve         Total Ore
Reserve
         

Commodity
Deposit(1)(2)(3)(4)(5)(6)(7)

  

Ore
Type

   Millions
of wet
metric
tonnes
   Grade    Millions
of wet
metric
tonnes
   Grade    Millions
of wet
metric
tonnes
   Grade    Mine
Life(3)
   Millions of
wet metric
tonnes
   Mine
Life(3)
   BHP
Billiton
Interest
%
         %Fe    %P    %SiO2    %A12O3    %LOI       %Fe    %P    %SiO2    %A12O3    %LOI       %Fe    %P    %SiO2    %A12O3    %LOI            

Iron Ore

                                                                    

Mt Newman JV(9)

   BKM    342    63.2    0.07    4.7    2.0    2.2    481    62.2    0.08    5.8    2.1    2.4    823    62.6    0.08    5.3    2.1    2.3    23    780    23    85
   MM    23    61.6    0.06    3.0    1.6    6.8    42    62.0    0.07    2.8    1.8    6.2    65    61.9    0.07    2.9    1.7    6.4       67      

Jimblebar(10)(11)

   BKM    99    63.2    0.09    3.5    2.4    3.4    326    62.6    0.10    3.3    2.4    4.1    425    62.7    0.10    3.3    2.4    3.9    61    253    32    100

Mt Goldsworthy JV
Northern
(12)

   NIM    8.9    59.5    0.06    9.6    1.7    3.0    15    59.1    0.05    10.8    1.1    2.4    24    59.2    0.05    10.4    1.3    2.6    12    3.2    2    85

Mt Goldsworthy JV
Area C
(13)(14)

   BKM    53    62.6    0.14    2.9    1.9    5.0    127    61.7    0.13    3.7    2.1    5.2    180    62.0    0.13    3.5    2.0    5.1    18    —      18    85
   MM    180    62.4    0.06    2.8    1.6    5.8    216    61.4    0.06    3.6    1.9    6.1    396    61.9    0.06    3.2    1.8    6.0       418      

Yandi JV(15)(16)

   CID    791    57.4    0.04    5.6    1.4    10.5    301    56.9    0.04    6.2    1.5    10.6    1,092    57.2    0.04    5.8    1.4    10.5    24    913    20    85
          Millions
of dry
metric
tonnes
   %Fe    %Pc                   Millions
of dry
metric
tonnes
   %Fe    %Pc                   Millions
of dry
metric
tonnes
   %Fe    %Pc                        Millions of
dry metric
tonnes
         

Samarco JV(17)

   ROM    451    43.9    0.05             173    44.0    0.05             624    44.7    0.05             21    480    17    50

 

 

(1)      The reserves are divided into joint ventures and material types that reflect the various products produced. The West Australian ore types are classified as per the host Archaean or Proteroz oic banded iron formations. Ore types are BKM – Brockman, MM – Marra Mamba, NIM – Nimingarra, CID – Channel Iron Deposit. ROM – Run of Mine for Samarco, comprising itabirites and friable hematite ores.

 

(2)      The reserve grades listed: Fe -iron, P-phosphorous, SiO2– silica, Al2O3 – alumina, LOI – loss on ignition,, refer to in situ mass percentage on a dry weight basis. For Mt Newman, Jimblebar, Mt Goldsworthy and Yandi joint ventures tonnages represent wet tonnes based on the following moisture contents: BKM – 3%, MM – 4%, CID – 8%, NIM – 3.5%. Iron ore is marketed as Lump (direct blast furnace feed) and Fines (sinter plant feed). For Samarco: %Pc – phosphorous in concentrate. Samarco is marketed predominantly as direct reduction and blast furnace pellets.

 

(3)      Metallurgical recovery is 100%, except for Mt Newman JV – Whaleback BKM where recovery is 92%. For Samarco, metallurgical recovery is 83.8%.

 

(4 )      Approximate drill hole spacings used to classify the reserves are:

 

  

 

(10)    Changes to Jimblebar are due to additional resource definition drilling, new geological interpretation, new resource modelling and new pit designs for Jimblebar W1/2/3, and a change in cut-off grade from 60%Fe to 59%Fe.

 

(11)    The Jimblebar Reserves listed include the Wheelarra Hill 3, 4 and Hashimoto 1 and 2 deposits at Jimblebar in which the Wheelarra Joint Venture participants (BHP Iron Ore (Jimblebar) Pty Ltd (51%), ITOCHU Minerals and Energy of Australia Pty Ltd (4.8%), Mitsui Iron Ore Corporation Pty Ltd (4.2%) and subsidiaries of Chinese steelmakers Magang, Shagang, Tanggang and Wugang (10% each) have a legal interest. At the commencement of the Wheelarra Joint Venture on 1 October 2005, the Wheelarra Joint Venture participants had a legal interest in 175 million dry metric tonnes of Jimblebar Reserves (Wheelarra Joint Venture tonnes). The effect of the sales contracts entered into between the Wheelarra Joint Venture participants and the Mt Newman Joint Venture participants and other associated agreements is that BHP Billiton (as a Mt Newman Joint Venture participant) has an entitlement to 85% of these Wheelarra Joint Venture tonnes. This disclosure and the financial statements are prepared on this basis.

 

(12)    Changes to Mt. Goldsworthy JV Northern are due to the inclusion of Cundaline, Nimingarra A and B deposits, and a change in cut-off from 58%Fe to 50%Fe for Cattle Gorge.

 

(13)    Changes to Mt Goldsworthy JV Area C are due to additional resource definition drilling, new geological interpretation and resource models for A Deposit, Packsaddle 1 and 3. New Reserve for Packsaddle 1 and 3 (BKM).

 

(14)    The Area C Reserves listed include C Deposit within Area C in which the POSMAC Joint Venture participants (BHP Billiton Minerals Pty Ltd (68%), ITOCHU Minerals and Energy of Australia Pty Ltd (6.4%), Mitsui Iron Ore Corporation Pty Ltd (5.6%) and a subsidiary of POSCO (a Korean steelmaker) (20%)) have a legal interest. The effect of the sales contracts entered into between the POSMAC Joint Venture participants and the Mt Goldsworthy Joint Venture participants and other associated agreements is that BHP Billiton (as a Mt Goldsworthy Joint Venture participant) has an entitlement to 85% of the reserves in C Deposit. This disclosure and the financial statements are prepared on this basis.

 

(15)    Changes to Yandi JV are due to a change in cut-off grade from 56%Fe to 55%Fe and 55.5%Fe, additional resource definition drilling, new geological interpretation and resource modelling for Yandi W1 and E4, and new pit designs.

 

(16)    The Yandi Reserves listed include the Western 4 deposit in which the JFE Western 4 Joint Venture (JW4 JV) participants BHP Billiton Minerals Pty Ltd (68%), ITOCHU Minerals and Energy of Australia Pty Ltd (6.4%), Mitsui Iron Ore Corporation Pty Ltd (5.6%) and a subsidiary of JFE Steel Corporation (a Japanese steelmaker) (20%)) have a legal interest. The effect of the sales contracts entered into between the JW4 JV participants and the Yandi Joint Venture participants and other associated agreements is that BHP Billiton (as a Yandi Joint Venture participant) has an entitlement to 85% of the Reserves in the Western 4 deposit. This disclosure and the financial statements are prepared on this basis.

 

(17)    During the feasibility studies for the Third Pelletizing Plant Project further drilling and changes to the resource classification has confirmed a reserve for more than 20 years of mine life. The reported reserve is inside the 2027 pit designed for the Third Pelletizing Plant Project.

      Proved Ore Reserves    Probable Ore Reserves   

Mt Newman JV

   50m x 50m    300m x 50m   

Jimblebar

   50m x 50m    300m x 50m   

Mt Goldsworthy JV Northern

   25m x 25m    50m x 50m   

Mt Goldsworthy JV Area C

   50m x 50m    300m x 50m   

Yandi JV

   50m x 50m    150m x 150m   

Samarco JV

   AL North: 200m x 200m x 16m    AL North: 400m x 400m x 16m   
   AL Centre: 200m x 200m x 16m    AL Centre: 400m x 400m x 16m   
     AL South: 200m x 200m x 16m    AL South: 400m x 400m x 16m   

 

(5)      Competent Persons – Mt Newman JV. Jimblebar, Mt Goldsworthy JV Northern and Area C, Yandi JV: R Pasyar (MAusIMM) J Kirk (MAusIMM). Samarco JV: J D da Silva (MAusIMM), L Rezende (MAusIMM), both employed by Samarco Mineraçáo SA.

 

(6 )      Some cut-off grades have been adjusted to align with revised product strategy. Cut-off grades used to estimate reserves: Mt Newman 50–62%Fe for BKM, 59%Fe for MM; Jimblebar 59%Fe for BKM; Mt Goldsworty 50%Fe for NIM, 57%Fe for MM, 59.5%Fe for BKM; Yandi 55–55.5%Fe for CID.

 

(7 )      Our Western Australian iron ore reserves are all located on State Agreement mining leases that guarantee the right to mine, except the Cattle Gorge mine (part of Mt Goldsworthy JV Northern), which is an operating mine on a standard Western Australian mining lease. We are required to obtain certain State Government approvals (including environmental and heritage clearances) before we commence mining operations on a particular area. We have included in our reserves areas where one or more approvals remain outstanding but where, based on the technical investigations we carry out as part of our mine planning process and our knowledge and experience of the approvals process, we expect that such approvals will be obtained as part of the normal course of business and within the timeframe required by the current life-of-mine schedule.

 

(8)      Mine life (years) is calculated as Total Reserve divided by current approved nominal production rate.

 

(9)      Changes to Mt Newman JV are due to additional resource definition drilling, new geological interpretation and resource models for Whaleback, 0B24, 0B25 Pit 4 and OB30, and changed MM and BKM (except Whaleback) cut-off grade from 60%Fe to 59%Fe.

  

 

- 6 -


Table 3. Manganese Mineral Resource Statement

Manganese Customer Sector Group

Mineral Resources

The tables below detail the total inclusive Mineral Resources for the Manganese Customer Sector Group estimated as at 30 June 2008 in 100 percent terms (unless otherwise stated).

 

As at 30 June 2008

                                                          As at 30 June 2008     
          Measured Resource    Indicated Resource    Inferred Resource    Total Resource    Total Resource     

Commodity
Deposit (1)(2)

  

Ore Type

   Millions
of dry
metric
tonnes
   Grade    Millions
of dry
metric
tonnes
   Grade    Millions
of dry
metric
tonnes
   Grade    Millions
of dry
metric
tonnes
   Grade    Millions
of dry
metric
tonnes
   Grade    BHP
Billiton
Interest
%
         %
Mn
   %
Yield
      %
Mn
   %
Yield
      %
Mn
   %
Yield
      %
Mn
   %
Yield
      %
Mn
   %
Yield
  

Manganese

                                                  

GEMCO (3)

   ROM    78    46.4    44    48    46.0    44    39    43.4    45    164    46.1    44    170    46.1    44    60
          Millions
of dry
metric
tonnes
   %
Mn
        Millions
of dry
metric
tonnes
   %
Mn
        Millions
of dry
metric
tonnes
   %
Mn
        Millions
of dry
metric
tonnes
   %
Mn
        Millions
of dry
metric

tonnes
   %
W1
lump
         

Wessels (4)(5)

   Lower Body    11    46.7       46    46.1       —      —         56    46.2       22    48.9       54.6
  

Upper Body (6)

   —      —         103    43.7       —      —         103    43.7       —      —        
          Millions
of wet
metric
tonnes
   %
Mn
   %
Fe
   Millions
of wet
metric
tonnes
   %
Mn
   %
Fe
   Millions
of Wet
metric
tonnes
   %
Mn
   %
Fe
   Millions
of wet
metric
tonnes
   %
Mn
   %
Fe
   Millions
of wet
metric

tonnes
   %
Mn
   %
Fe
    

Mamatwan (4)(7)

   M. C and N Zones    59    37.6    4.5    25    36.8    4.5    7.3    36.5    4.6    90    37.3    4.5    68    37.1    4.84    54.6
  

X zone

   7.0    37.2    4.8    1.9    36.5    4.7    0.5    35.9    4.4    9.4    37.0    4.8    —      —      —     
  

Top cut (Balance)

   30    31.1    6.4    16    30.3    6.2    4.5    30.3    6.2    50    30.8    6.3    —      —      —     

 

(1)      Competent Persons – Resources

 

GEMCO: E P W Swindell (SACNASP)

Wessels: E P Ferreira (SACNASP)

Mamatwan: O van Antwerpen (SACNASP)

 

(2)      The Mineral Resources are reported after adjustment for depletion due to mining (actual production from 1 July 2007 to 30 April 2008 and forecast production for May and June 2008).

 

(3)       GEMCO – ROM – run of mine product . Manganese grades (%Mn ) are given as per washed ore samples and should be read together with their respective yields. Culturally significant areas have been excised from the resources (G Quarry Rainforest) adjacent to the local community. This excision equates to 3.2Mt of ROM.

 

(4)      An agreement has been signed between Samancor Manganese and empowerment consortium Ntsimbintle Mining Pty Ltd. The Ntsimbintle agreement has been signed by both parties but remains subject to Government approval which is believed to be administrative in nature. This transaction allows for the inclusion of part of the Prospecting Rights held by Ntsimbintle into the Wessels and Mamatwan Mining Areas in exchange for 9% equity in Hotazel Mines, thereby adding the resources within the Ntsimbintle Prospecting Right to the Wessels and Mamatwan Mining Rights. The BHP Billiton share of Wessels and Mamatwan mines (Hotazel Manganese Mines) therefore drops from 60% to 54.6%.

 

(5)      The Mn cut-off grade at Wessels has been lowered from 45% to 37.5% due to the following: Wessels Mine has historically been a high grade mine – mean Manganese (Mn) content for W1Lump being 48%. As a result only this high grade portion was previously declared while a low grade portion, W4Lump at a mean grade of 41.1%Mn, was not declared. Selling of this low grade product is dependent on marketing requirements. Positive changes in market conditions now allow for the inclusion of all grades above a cut-off of 37.5%Mn. The traditional W1Lump at a mean grade of 48% was also adjusted to 47%Mn.

 

(6)      The addition of the Upper Body to the Wessels Mine Mineral Resource arises from a process of extensive evaluation during FY2008, including the development of an ore body model largely based upon an extensive drilling database accumulated over the history of the mine.

 

(7)      At Mamatwan, the X Zone and Top Cut (Balance) have not previously been declared as Mineral Resource in the Annual Report. As a matter of course, this material has to be mined in the process of accessing the economic X, M, C and N zones, and due to positive market conditions, this material now has potential economic value.

 

- 7 -


IMPORTANT NOTICES

Certain statements in this news release are forward-looking statements (including statements regarding the identification of additional mineral Reserves and Resources) that are based on current expectations and beliefs. These expectations and beliefs may or may not prove to be correct and, by their nature, are subject to a number of known and unknown risks and uncertainties that could cause actual results, performance and achievements to differ materially.

Cautionary Note to US Investors – The US Securities and Exchange Commission (“SEC”) generally permits mining companies in their filings with the SEC to disclose only those mineral deposits that the company can economically and legally extract. Certain terms in this presentation, including “resource”, “indicated resource”, “inferred resource” and “measured resource”, would not generally be permitted in an SEC filing. The material denoted by such terms is not proven or probable Reserves as such terms are used in the SEC’s Industry Guide 7, and there can be no assurance that BHP Billiton will be able to convert such material to proven or probable Reserves or extract such material economically. Although the iron ore Reserves presented in this news release have been calculated in accordance with Industry Guide 7, BHP Billiton urges investors to refer to its Annual Report on Form 20-F for the fiscal year ended 30 June, 2007 for its most recent statements of its other mineral Reserves calculated in accordance with Industry Guide 7.

Information Relating to the US Offer for Rio Tinto plc

BHP Billiton plans to register the offer and sale of securities it would issue to Rio Tinto plc US shareholders and Rio Tinto plc ADS holders by filing with the SEC a Registration Statement (the “Registration Statement”), which will contain a prospectus (the “Prospectus”), as well as other relevant materials. No such materials have yet been filed. This communication is not a substitute for any Registration Statement or Prospectus that BHP Billiton may file with the SEC.

U.S. INVESTORS AND U.S. HOLDERS OF RIO TINTO PLC SECURITIES AND ALL HOLDERS OF RIO TINTO PLC ADSs ARE URGED TO READ ANY REGISTRATION STATEMENT, PROSPECTUS AND ANY OTHER DOCUMENTS MADE AVAILABLE TO THEM AND/OR FILED WITH THE SEC REGARDING THE POTENTIAL TRANSACTION, AS WELL AS ANY AMENDMENTS AND SUPPLEMENTS TO THOSE DOCUMENTS, WHEN THEY BECOME AVAILABLE BECAUSE THEY WILL CONTAIN IMPORTANT INFORMATION.

Investors and security holders will be able to obtain a free copy of the Registration Statement and the Prospectus as well as other relevant documents filed with the SEC at the SEC’s website (http://www.sec.gov), once such documents are filed with the SEC. Copies of such documents may also be obtained from BHP Billiton without charge, once they are filed with the SEC.

Information for US Holders of Rio Tinto Limited Shares

BHP Billiton Limited is not required to, and does not plan to, prepare and file with the SEC a registration statement in respect of the Rio Tinto Limited Offer. Accordingly, Rio Tinto Limited shareholders should carefully consider the following:

The Rio Tinto Limited Offer will be an exchange offer made for the securities of a foreign company. Such offer is subject to disclosure requirements of a foreign country that are different from those of the United States. Financial statements included in the document will be prepared in accordance with foreign accounting standards that may not be comparable to the financial statements of United States companies.

Information Relating to the US Offer for Rio Tinto plc and the Rio Tinto Limited Offer for Rio Tinto shareholders located in the US.

It may be difficult for you to enforce your rights and any claim you may have arising under the U.S. federal securities laws, since the issuers are located in a foreign country, and some or all of their officers and directors may be residents of foreign countries. You may not be able to sue a foreign company or its officers or directors in a foreign court for violations of the U.S. securities laws. It may be difficult to compel a foreign company and its affiliates to subject themselves to a U.S. court’s judgment.

You should be aware that BHP Billiton may purchase securities of either Rio Tinto plc or Rio Tinto Limited otherwise than under the exchange offer, such as in open market or privately negotiated purchases.

Further BHP Billiton information can be found on our Internet site: http://www.bhpbilliton.com

 

Australia

Samantha Evans, Media Relations

Tel: +61 3 9609 2898 Mobile: +61 400 693 915

email: Samantha.Evans@bhpbilliton.com

 

Leng Lau, Investor Relations

Tel: +61 3 9609 4202 Mobile: +61 403 533 706

email: Leng.Y.Lau@bhpbilliton.com

 

United States

Tracey Whitehead, Investor & Media Relations

Tel: US +1 713 599 6100 or UK +44 20 7802 4031

Mobile: +44 7917 648 093

email: Tracey.Whitehead@bhpbilliton.com

 

United Kingdom & South Africa

Andre Liebenberg, Investor Relations

Tel: +44 20 7802 4131 Mobile: +44 7920 236 974

email: Andre.Liebenberg@bhpbilliton.com

 

Illtud Harri, Media Relations

Tel: +44 20 7802 4195 Mobile: +44 7920 237 246

email: Illtud.Harri@bhpbilliton.com

 

- 8 -