For the month of June, 2008
Cameco Corporation
(Commission file No. 1-14228)
2121 11th Street West
Saskatoon, Saskatchewan, Canada S7M 1J3
(Address of Principal Executive Offices)
Indicate by check mark whether the registrant files or will file annual reports under cover Form
20-F or Form 40-F.
Indicate by check mark whether the registrant by furnishing the information contained in this Form
is also thereby furnishing the information to the Commission pursuant to Rule 12g3-2(b) under the
Securities Exchange Act of 1934.
If Yes is marked, indicate below the file number assigned to the registrant in connection with
Rule 12g3-2(b):
|
|
|
|
|
TSX: CCO
NYSE: CCJ
|
|
|
|
website: cameco.com
currency: Cdn |
2121 11th Street West, Saskatoon, Saskatchewan, S7M 1J3 Canada
Tel: (306) 956-6200 Fax: (306) 956-6201
Cameco Updates Progress at Cigar Lake
Saskatoon, Saskatchewan, Canada, June 27, 2008. . . . . . . . . . . . . . . . . . . . . . . . . . . .
Cameco Corporation announced today it continues to make progress with remediation at the Cigar Lake
uranium project.
Cameco previously submitted an application to the Canadian Nuclear Safety Commission (CNSC) to
allow dewatering of the underground development and all other remediation activities leading up to,
but not including, the restart of construction underground.
The CNSC and the Saskatchewan Ministries of Environment and Advanced Education, Employment and
Labour have approved Camecos plans to pump the water out of the mine and to inspect and safely
secure the mine once it is pumped out.
The remainder of the remediation activities specified in the application, including completion of
the second shaft and other activities, are under regulatory review. A public hearing before the
CNSC is scheduled for September 18, 2008 to formally consider the application.
As previously reported, in February 2008, the underground seal was found effective in a test
consisting of lowering the water level in the shaft to 100 metres below surface. In addition, as
reported in the first quarter report of 2008, Cameco completed an assessment of two areas of the
mine and determined that no additional reinforcement or other precautionary measures were required
prior to dewatering.
We expect to pump water out of the mine over several months beginning next week. This will allow us
to equip the mine shaft with a ladderway, ventilation ducting, power and communication cables,
water pipes and other necessary equipment as the water level goes down. The integrity of the plug
will also be assessed at each stage of the process.
We continue to anticipate production startup in 2011 at the earliest. We will be able to provide a
firmer production date after the water has been pumped out of the mine, the condition of the
underground development has been assessed, and the findings incorporated in the new mine
development and production plans.
Cameco owns 50% and is operator of the Cigar Lake project located in northern Saskatchewan.
3
Caution Regarding Forward-Looking Information and Statements
The above Cigar Lake expected production date and certain other statements regarding our plans and
expectations for the dewatering and resumption of production are forward-looking information and
are based upon the following key assumptions and subject to a number of factors that could cause
results to differ materially:
|
|
|
we have assumed that our remediation plan and our plans to complete the partially
completed second shaft and underground development will succeed and be completed in a
timely manner, but that is subject to a number of risks including that the plans do not
work as anticipated or takes longer to complete due to construction and other delays; |
|
|
|
|
we have made certain assumptions regarding the timing of regulatory approvals, including
for conducting surface construction and remediation activities, completing the second
shaft, re-commencing underground development and commencing production, but that is subject
to a number of risks including that the regulatory approvals take longer to obtain than
anticipated; |
|
|
|
|
we have assumed that information regarding the condition of the existing underground
workings, which condition will not be known until the mine has been dewatered, will not
adversely impact our mine and development and production plans in a material way, but that
is subject to a number of risks including that underground workings are materially damaged
causing material delays to our plans; and |
|
|
|
|
we have assumed there is no disruptions to our plans due to among other things: natural
phenomena, such as fires, floods or cave-ins; the occurrence of another water inflow at
Cigar Lake; failure of our radiation protection plans; labour disputes; litigation or
arbitration proceedings; delay in obtaining or failure to procure the required equipment,
operating parts and supplies; equipment failure; a delay in or an inability to obtain the
necessary permits and approvals; failure to adhere to regulatory permits and approvals;
unexpected geological conditions, including weak ground conditions, or unexpected
hydrological conditions, including due to the failure to control ground water; and adverse
ground conditions (Cigar Lake risks). The Company is subject to the risk that one or more
of the Cigar Lake risks may occur as well as other development or operating risks
associated with Cigar Lake, which is a challenging deposit to develop and mine. |
If actual results differ materially from the assumptions set out above or if any of the material
factors above occur, the Cigar Lake production restart date may differ materially from the expected
date that is stated above.
Although Cameco believes the assumptions inherent in these forward-looking statements are
reasonable, undue reliance should not be placed on these statements which only apply as of the date
of this news release. Cameco disclaims any intention or obligation to update or revise any
forward-looking statement, whether as the result of new information, future events or otherwise.
4
Qualified person
The above scientific and technical information for Cigar Lake was prepared under the supervision of
C. Scott Bishop, a professional engineer employed by Cameco as the chief mine engineer of the Cigar
Lake project and a qualified person for the purpose of National Instrument 43-101.
Profile
Cameco, with its head office in Saskatoon, Saskatchewan, is the worlds largest uranium producer.
The companys uranium products are used to generate electricity in nuclear energy plants around the
world, providing one of the cleanest sources of energy available today. Camecos shares trade on
the Toronto and New York stock exchanges.
- End -
|
|
|
|
|