For the month of December, 2007
Cameco Corporation
(Commission file No. 1-14228)
2121-11th Street West
Saskatoon, Saskatchewan, Canada S7M 1J3
(Address of Principal Executive Offices)
Indicate by check mark whether the registrant files or will file annual reports under cover
Form 20-F or Form 40-F.
Form 20-F o Form 40-F þ
Indicate by check mark whether the registrant by furnishing the information contained in this Form
is also thereby furnishing the information to the Commission pursuant to Rule 12g3-2(b) under the
Securities Exchange Act of 1934.
Yes o No þ
If Yes is marked, indicate below the file number assigned to the registrant in connection with
Rule 12g3-2(b):
Exhibit Index
|
|
|
|
|
Exhibit No. |
|
Description |
|
Page No. |
1.
|
|
Press Release dated
December 19, 2007
|
|
3 - 7 |
SIGNATURE
Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused
this report to be signed on its behalf by the undersigned, thereunto duly authorized.
|
|
|
|
|
Date: December 20, 2007 |
|
Cameco Corporation
|
|
|
By: |
Gary M.S. Chad |
|
|
|
Gary M.S. Chad, Q.C.
Senior Vice-President, Governance,
Law and Corporate Secretary |
|
|
-2-
|
|
|
|
|
TSX: CCO
NYSE: CCJ
|
|
|
|
website: cameco.com
currency: Cdn |
2121 11th Street West, Saskatoon, Saskatchewan, S7M 1J3 Canada
Tel: (306) 956-6200 Fax: (306) 956-6201
Cameco Provides Scheduled Update on Cigar Lake
Company also provides Rabbit Lake update
Saskatoon, Saskatchewan, Canada, December 19, 2007. . . . . . . . . . . . . .
Cameco Corporation is providing a scheduled update on the activities underway at the Cigar Lake
uranium project. The company is maintaining the previously announced expected production restart
date.
Construction was about 60% complete when we experienced a rockfall causing a flood of the
underground development in October 2006. Site crews continue to make progress on the remediation
plan and we believe that the water inflow has been essentially sealed off. The next major milestone
is dewatering the mine.
Activities for Achieving Dewatering
Concrete plug
The concrete barrier plug has been completed after pouring approximately 1,000 cubic metres of
concrete in the tunnel in the vicinity of the original inflow and grouting around it to seal it
off. We poured an additional 1,000 cubic metres of concrete behind the concrete barrier plug and up
into the area above the rockfall where the water inflow began. We are now in the final stages of
grouting above the inflow area and filling the drill holes used in the remediation process.
We plan to conduct a preliminary test of the effectiveness of the plug and sealed rockfall area by
drawing down the water level in the shaft to an intermediate stage and measuring the water inflow.
We expect to complete this test before the end of February. The plug and seal will be considered
effective if the total mine water inflow is limited to a rate considered safe for mine re-entry.
Dewatering is planned to proceed after the plug and seal are proven to be effective.
Assessments
Prior to dewatering, we need to complete a geotechnical assessment to determine if
depressurization, reinforcement or other precautionary measures are necessary in two other areas of
the mine. To ascertain this, we are drilling a number of holes to assess the pore water pressure,
as well as rock quality and structure in these two areas. Five of six holes have been
-3-
completed
and we expect results from this assessment to be available in the first quarter of 2008. We can
then assess if any additional remediation is required in these areas.
Dewatering Timeline
In addition to the technical work, we need to complete the corrective actions we committed to do
following the root cause investigation, as well as receive certain regulatory approvals. Cameco
must have all these activities completed before applying for regulatory approval to dewater.
Accordingly, we are targeting completion of dewatering in the second half of 2008. (Please see the
cautionary note regarding forward-looking information below.)
Other Cigar Lake Activities
Licence Amendment
As previously indicated, the Canadian Nuclear Safety Commission (CNSC) announced, on December 3,
2007, it had amended the construction licence for the Cigar Lake project. The licence will be valid
for two years until December 31, 2009.
Subsequent amendments to the construction licence will be required to complete remediation and
resume pre-flood underground construction and development activities.
Surface Construction
Construction activities currently underway at the site include mine ventilation fans installation
on surface, the slurry load-out facilities and surface pipelines.
There are about 125 Cameco employees employed at Cigar Lake and about 200 contractors on site.
Production Restart
The expected production startup date continues to be 2011 at the earliest, as previously announced.
(Please see the cautionary note regarding forward-looking information below). We will be able to
provide a firmer production startup date after the mine has been dewatered and the condition of the
underground development has been assessed and the findings incorporated in the new mine development
and production plans.
Next Update
We will provide an update on the activities at the Cigar Lake project when we release the year end
financial results.
Cautionary Note Regarding Forward-Looking Information
The above Cigar Lake expected production date and certain other statements regarding our plans
and expectations for the resumption of production are forward-looking information and are based
-4-
upon the following key assumptions and subject to a number of factors that could cause results to
differ materially:
|
|
|
we have assumed that our remediation plan and our plans to complete the partially
completed second shaft and underground development will succeed and be completed in a
timely manner, but that is subject to a number of risks including that the plans do not
work as anticipated or take longer to complete due to construction and other delays; |
|
|
|
we have made certain assumptions regarding the timing of regulatory approvals, including
for conducting surface construction and remediation activities, completing the second
shaft, re-commencing underground development and commencing production, but that is subject
to a number of risks including that the regulatory approvals take longer to obtain than
anticipated; |
|
|
|
we have assumed that information regarding the condition of the existing underground
workings, which condition will not be known until the mine has been dewatered, will not
adversely impact our mine and development and production plans in a material way, but that
is subject to a number of risks including that underground workings are materially damaged
causing material delays to our plans; and |
|
|
|
we have assumed there are no disruptions to our plans due to among other things: natural
phenomena, such as fires, floods or cave-ins; the occurrence of another water inflow at
Cigar Lake (the planned freezing of the orebody is expected to reduce, but not eliminate
the risk of another water inflow); failure of our radiation protection plans, including
associated with freezing the orebody; labour disputes; litigation or arbitration
proceedings; delay in obtaining or failure to procure the required equipment, operating
parts and supplies; equipment failure; a delay in or an inability to obtain the necessary
permits and approvals, including due to the companys failure to complete in a timely
manner its corrective actions committed to the CNSC in response to the two Cigar Lake
water; failure to adhere to regulatory permits and approvals; unexpected geological
conditions, including weak ground conditions, or unexpected hydrological conditions,
including due to the failure to control ground water; and adverse ground conditions (Cigar
Lake risks). The company is subject to the risk that one or more of the Cigar Lake risks
may occur as well as other development or operating risks associated with Cigar Lake, which
is a challenging deposit to develop and mine. |
If actual results differ materially from the assumptions set out above or if any of the material
factors above occur, the Cigar Lake production restart date may differ materially from the expected
date that is stated above.
The statements above regarding the expected date for the completion of Cigar Lake dewatering under
the heading Dewatering Timeline and certain other statements regarding our planned activities
under the headings Concrete plug and Assessments are forward-looking information and are based
upon the following key assumptions and subject to a number of factors that could cause results to
differ materially:
|
|
|
we have assumed testing of the plug and seal, as outlined above, will confirm that the
total mine water inflow is limited to a rate considered safe for mine re-entry and the |
-5-
|
|
|
testing will be completed as planned, but that is subject to a number of risks including
that testing shows that the plug is not working as anticipated; |
|
|
|
we assumed that the geotechnical assessments of the two other areas of the mine, as
outlined above, will be completed as planned and will not require the company to proceed
with additional precautionary measures, but that is subject to a number of risks including
that the assessments require the company to proceed with significant additional
precautionary measures; and |
|
|
|
we have assumed that there is no disruption in our plans to complete dewatering due to
the occurrence of one or more Cigar Lake risks, as defined above. The company is subject to
the risk that one or more of the Cigar Lake risks may occur as well as other development or
operating risks associated with Cigar Lake, which is a challenging deposit to develop and
mine. |
If actual results differ materially from the assumptions set out above or if any of the material
factors above occur, the expected date for completion of Cigar Lake dewatering may differ
materially from the above forecast.
Although Cameco believes the assumptions inherent in these forward-looking statements are
reasonable, undue reliance should not be placed on these statements which only apply as of the date
of this news release. Cameco disclaims any intention or obligation to update or revise any
forward-looking statement, whether as the result of new information, future events or otherwise.
Qualified Person
The above scientific and technical information for Cigar Lake was prepared under the supervision of
C. Scott Bishop, a professional engineer employed by Cameco as the chief mine engineer of the Cigar
Lake project and a qualified person for the purpose of National Instrument 43-101.
Rabbit Lake Update
As announced in late November 2007, Camecos Rabbit Lake underground mine experienced
increased water inflow and mining was suspended. Currently the amount of water entering and leaving
the mine is essentially in balance and site crews are in the process of permanently sealing off the
affected area. We have only used a maximum of about 4% of the designated underground storage
capacity.
Planned upgrades to the water handling system were completed in the first week of December well
ahead of schedule.
We have finished pouring four concrete barriers, or bulkheads to seal off the area from increased
water inflow. We built two bulkheads on the 90-metre level and two on the 105-metre level. We
expect it will take about three to five weeks for the concrete in the bulkheads to cure and to
complete the associated grouting of the seal. We will not start mining until we have sufficiently
-6-
curtailed the water inflow, to re-establish an adequate margin of water handling capacity.
We have determined that the additional water is entering the area through a decades-old,
exploration drill hole. We are in the process of preparing to plug the drill hole.
In 2007, Cameco has produced 4.0 million pounds of uranium at Rabbit Lake which is the estimated
annual production for the year. We will reassess 2008 production and provide an updated forecast
when mining and milling plans are finalized.
Cameco Corporation
Cameco, with its head office in Saskatoon, Saskatchewan, is the worlds largest uranium producer.
The companys uranium products are used to generate electricity in nuclear energy plants around the
world, providing one of the cleanest sources of energy available today. Camecos shares trade on
the Toronto and New York stock exchanges.
- End -
|
|
|
|
|