e6vk
UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, DC 20549
FORM 6-K
Report of Foreign Private Issuer
Pursuant to Rule 13a-16 or 15d-16 Under
the Securities Exchange Act of 1934
For the month of November, 2006
Cameco Corporation
(Commission file No. 1-14228)
2121 11th Street West
Saskatoon, Saskatchewan, Canada S7M 1J3
(Address of Principal Executive Offices)
Indicate by check mark whether the registrant files or will file annual reports under cover
Form 20-F or Form 40-F.
Indicate by check mark whether the registrant by furnishing the information contained in this Form
is also thereby furnishing the information to the Commission pursuant to Rule 12g3-2(b) under the
Securities Exchange Act of 1934.
If Yes is marked, indicate below the file number assigned to the registrant in connection with
Rule 12g3-2(b):
Exhibit Index
|
|
|
|
|
Exhibit No. |
|
Description |
|
Page No. |
|
|
|
|
|
1.
|
|
Material Change Report dated
November 1, 2006
|
|
3-4 |
SIGNATURE
Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused
this report to be signed on its behalf by the undersigned, thereunto duly authorized.
|
|
|
|
|
Date: November 1, 2006 |
Cameco Corporation
|
|
|
By: |
"Gary M.S. Chad"
|
|
|
|
Gary M.S. Chad |
|
|
|
Senior Vice-President, Governance,
Legal and Regulatory Affairs, and
Corporate Secretary |
|
2
FORM 51-102F3
MATERIAL CHANGE REPORT
Item 1 Name and Address of Company
Cameco Corporation (Cameco)
2121 11th Street West, Saskatoon, Saskatchewan S7M 1J3
Item 2 Date of Material Change
October 23, 2006
Item 3 News Release
The English versions and the French translation versions of the two press releases relating to this
material change were distributed and filed by Canadian Corporate News through their Canadian Timely
Disclosure Pack and U.S. Timely Disclosure Pack on October 23, 2006.
Item 4 Summary of Material Change
On October 23, 2006, Cameco reported a second water inflow at Cigar Lake following a rock fall on
October 22, 2006 in a future production area that had been previously dry. Efforts to protect the
main shaft and key underground infrastructure by closing the bulk head doors were unsuccessful. All
underground areas of the Cigar Lake project have filled with water. Everyone was safely evacuated
from the mine, no injuries were sustained and there was no impact on the environment. Cigar Lake
production was expected in 2008 prior to the water inflow incident. Cameco is investigating
options to restore access to the mine.
Item 5 Full Description of Material Change
On October 23, 2006, Cameco reported a second water inflow at Cigar Lake following a rock fall on
October 22, 2006 in a future production area that had been previously dry. Efforts to protect the
main shaft and key underground infrastructure by closing the bulk head doors were unsuccessful. All
underground areas of the Cigar Lake project have filled with water. Everyone was safely evacuated
from the mine, no injuries were sustained and there was no impact on the environment. Cigar Lake
production was expected in 2008 prior to the water inflow incident.
Cameco is investigating options to restore access to the mine. Production start up was previously
planned for early 2008 and the company will assess a new production timetable after remediation
plans are developed. Cameco is operator and majority owner of the Cigar Lake project in northern
Saskatchewan.
The incident began at 1:10 p.m. on Sunday, October 22, 2006, in the future production area that
previously had been dry. At 8:45 p.m., in accordance with existing contingency plans, the company
decided to close two bulkhead doors to contain the water inflow within the future mining areas. The
doors were closed at 5:00 a.m. on Monday, October 23, 2006. While monitoring the area, the company
found that one of the doors did not seal properly which allowed significant water to flow into the
processing area. Efforts to fully the seal the doors were not successful and the inflow exceeded
capacity to pump out the water.
3
Cameco is committed to develop plans to remediate the project and preserve this valuable asset.
Cameco will develop new timelines for construction, cost estimates and production forecasts. The
capital cost is expected to be significantly higher.
Cameco has supply interruption in its contracts providing the right to reduce, defer, or cancel
volumes on a pro-rata basis if the company experiences a shortfall in planned production. This
language protects about three-quarters of current contracted volumes. This percent will rise as old
contracts expire. All contracts also contain standard force majeure protection. The baseload
contracts put in place to support the development of Cigar Lake also contain supply interruption
language, which allows Cameco to reduce, defer or terminate Cigar Lake product deliveries in the
event of any delay or shortfall in Cigar Lake production. Given the foregoing contractual
protections, Cameco is adequately positioned to meet its contractual obligations.
On October 31, 2006, Cameco issued its report for the quarter ending September 30, 2006. This
report has been filed with securities regulators. This report contains additional information
regarding this material change, including an analysis of the implications to reserve classification
at Cigar Lake. Therefore, the reader of this material change report should also review the
disclosure relating to the incident contained in Camecos October 31, 2006 report.
The Cigar Lake project is located 660 kilometres north of Saskatoon with a workforce of 650 during
the construction phase. The Cigar Lake mine is owned by Cameco Corporation (50%), AREVA Resources
Canada Inc. (37%), Idemitsu Uranium Exploration Canada Ltd.(8%) and Tepco Resources Inc. (5%).
Item 6 Reliance on subsection 7.1(2) or (3) of National Instrument 51-102.
Not applicable.
Item 7 Omitted Information
Not applicable.
Item 8 Executive Officer
Gary M.S. Chad
Senior Vice-President, Governance, Legal and Regulatory Affairs, and
Corporate Secretary
Cameco Corporation
(306) 956-6303
Item 9 Date of Report
November 1, 2006.
4